問題1
An activity-relationship-activity path is cyclical and you are not able to schedule the network. Which analysis tool enables you to detect cyclical relationships and correct them?
Please choose the correct answer.
Response:

正確答案: C
問題2
Workforce Planning in Project Systems, allows you to assign certain HR resources to activities of a project.
Which of the following can be assigned?
There are 3 correct answers to this question.
Response:

正確答案: A,B,D
問題3
In Structure Information System which transactions allow you to analyze and edit the entire hierarchical structure of a project including documents, PS texts, networks, other orders, investment programs, and SD documents?
There are 2 correct answers to this question.
Response:

正確答案: A,B
問題4
What do you use in the parameters for network type to specify whether a workflow is to be generated in the case of purchase order relevant change?
Please choose the correct answer.
Response:

正確答案: A
問題5
You can maintain the following objects in the Project Builder. (4)

正確答案: A,B,C,F
問題6
Based on which of the following; reservations or purchase requisitions can automatically be created for a project?
There are 2 correct answers to this question.
Response:

正確答案: B,C
問題7
How do you derive the hierarchy of a work breakdown structure from the numbers of their WBS elements?
Please choose the correct answer.
Response:

正確答案: D
問題8
You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose?
Please choose the correct answer.
Response:

正確答案: B
問題9
Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning?
Please choose the correct answer.
Response:

正確答案: B
問題10
You use a WBS Project Structure with networks and maintenance orders. You want to Schedule both the networks and the maintenance orders. What do you consider? *

正確答案: D
問題11
Assume a scenario where deviations from the project plan occurred as a result of delivery problems, price fluctuations, and unforeseeable capacity bottlenecks.
How do you ensure that claims resulting from deviations are prepared for contractual partners and submitted to them at suitable point of time?
Please choose the correct answer.
Response:

正確答案: B
問題12
Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing?
There are 2 correct answers to this question.
Response:

正確答案: D,E
問題13
Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM?
Please choose the correct answer.
Response:

正確答案: D
問題14
Which of the following are controlled using plant and order type parameters?
There are 2 correct answers to this question.
Response:

正確答案: C,D
問題15
What are the prerequisites for automatic requirements grouping on the top WBS element of a project?
There are 2 correct answers to this question.
Response:

正確答案: C,E

專業認證

NewDumps模擬測試題具有最高的專業技術含量,只供具有相關專業知識的專家和學者學習和研究之用。

品質保證

該測試已取得試題持有者和第三方的授權,我們深信IT業的專業人員和經理人有能力保證被授權産品的質量。

輕松通過

如果妳使用NewDumps題庫,您參加考試我們保證96%以上的通過率,壹次不過,退還購買費用!

Try Before Buy

NewDumps提供每種産品免費測試。在您決定購買之前,請試用DEMO,檢測可能存在的問題及試題質量和適用性。