問題1
You have been asked to set up one active person, who is not a team member in the project, as a quality manager for each quality task created under projects. However, when you try to assign the quality manager as Task Manager, you cannot find the person's name in the list of values. What is the reason for this problem?
(Choose the best answer.)
You have been asked to set up one active person, who is not a team member in the project, as a quality manager for each quality task created under projects. However, when you try to assign the quality manager as Task Manager, you cannot find the person's name in the list of values. What is the reason for this problem?
(Choose the best answer.)
正確答案: B
說明:(僅 NewDumps 成員可見)
問題2
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
正確答案: B
說明:(僅 NewDumps 成員可見)
問題3
As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes In HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers.
Whichthreeare parameters that are based on which the system identifies the new resources?
As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes In HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers.
Whichthreeare parameters that are based on which the system identifies the new resources?
正確答案: B,C,D
說明:(僅 NewDumps 成員可見)
問題4
Your customer wants a team member who is assigned to a project to beable to create and submit a forecast, butnot to be able to approve the forecast. What is the default project role that you should assign to the person in the project to meet this requirement? (Choose the best answer.)
Your customer wants a team member who is assigned to a project to beable to create and submit a forecast, butnot to be able to approve the forecast. What is the default project role that you should assign to the person in the project to meet this requirement? (Choose the best answer.)
正確答案: B
說明:(僅 NewDumps 成員可見)
問題5
You are set up as a Follower in Manage Tasks. Which two abilities can you accomplish? (Choose two.)
You are set up as a Follower in Manage Tasks. Which two abilities can you accomplish? (Choose two.)
正確答案: A,B
說明:(僅 NewDumps 成員可見)
問題6
Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this.(Choose the best answer.)
Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this.(Choose the best answer.)
正確答案: D
說明:(僅 NewDumps 成員可見)
問題7
Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.
What are three conditions for new employees to show up in the list? (Choose three.)
Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.
What are three conditions for new employees to show up in the list? (Choose three.)
正確答案: A,B,C
說明:(僅 NewDumps 成員可見)
問題8
Your organization performs revenue recognition based on the Labor and Non-labor Burden schedule types.
Identify the setup required to enable this kind of revenue recognition. (Choose the best answer.)
Your organization performs revenue recognition based on the Labor and Non-labor Burden schedule types.
Identify the setup required to enable this kind of revenue recognition. (Choose the best answer.)
正確答案: C
問題9
Your organization has been awarded a new contract based on which you are allowed to sell:
* Items not tracked in inventory
* Inventory items
* Services
Which contract structure would fulfill your requirement of item sales? (Choose the best answer.)
Your organization has been awarded a new contract based on which you are allowed to sell:
* Items not tracked in inventory
* Inventory items
* Services
Which contract structure would fulfill your requirement of item sales? (Choose the best answer.)
正確答案: C
問題10
You are trying to create a custom infolet but are not able to find the "Create Infolet" option in the Infolet repository window. Whichtwosteps should be completed before you can access the "Create Infolet" option?
You are trying to create a custom infolet but are not able to find the "Create Infolet" option in the Infolet repository window. Whichtwosteps should be completed before you can access the "Create Infolet" option?
正確答案: B,D
說明:(僅 NewDumps 成員可見)