Your customer has separate organizations to maintain indirect, capital, and billing types of projects.
Identify the two setups that can be used to fulfill this requirement. (

正確答案: A,E
說明:(僅 NewDumps 成員可見)
問題2
Your customer accounts revenuebased on,product class category. Because all your customer's projects are funded by private and government institutions, they decide to classify all projects based on their funding source to accurately report on revenue in General Ledger. Accordingly, you create a new class category
"Funding Source" and assign it to all projects. However, you notice that the accounting is still happening based on product class category.Identify the reason for this problem. (Choose the best answer.)

正確答案: A
說明:(僅 NewDumps 成員可見)
問題3
Whichthreefile-based data imports are available for use in Oracle Project Portfolio Management Cloud?

正確答案: B,C,D
說明:(僅 NewDumps 成員可見)
問題4
Your customer wants additional project information for detailed account balance maintenance, reconciliation, and reporting. Identify the configuration in subledger accounting that can be set up to fulfill this requirement.
(Choose the best answer.)

正確答案: E
說明:(僅 NewDumps 成員可見)
問題5
Whichthreeare true of what you can do in the Project Requirements work area?

正確答案: B,C,D
說明:(僅 NewDumps 成員可見)
問題6
You want tocreate a few project roles so as to restrict accessin the Project Financial Management work area to only the specific projects in which an employee is assigned as a team member. What are the two default project roles available to meet this requirement? (Choose two.)

正確答案: B,E
說明:(僅 NewDumps 成員可見)
問題7
You have projects and tasks defined with transaction controls, which does not allow certain types of charges to the project. Your business needs to create invoices in AP with this project every period and hence would like to make the process easier by creating a distribution set. As you create the distribution set, you notice that thesedistribution set lines are not validated against the project transaction controlsand you are allowed to save it without any validation errors.Identify the why the project transaction controls are not applied. ( Choose the best answer.)

正確答案: C
說明:(僅 NewDumps 成員可見)
問題8
You have been asked to set up one active person, who is not a team member in the project, as a quality manager for each quality task created under projects. However, when you try to assign the quality manager as Task Manager, you cannot find the person's name in the list of values. What is the reason for this problem?
(Choose the best answer.)

正確答案: B
說明:(僅 NewDumps 成員可見)
問題9
Your customer wants to assign the Net 45 payment term to all sets except for the corporate business unit specific set, which is assigned the Net 15 payment term. At transaction entry, the list of values for payment terms consists of only one set of data: the set that is assigned to the transaction's business unit.
Which reference data sharing method would you set up to meet the customer requirement? (Choose the best answer.)

正確答案: B
說明:(僅 NewDumps 成員可見)
問題10
You are set up as a Follower in Manage Tasks. Which two abilities can you accomplish? (Choose two.)

正確答案: A,B
說明:(僅 NewDumps 成員可見)

專業認證

NewDumps模擬測試題具有最高的專業技術含量,只供具有相關專業知識的專家和學者學習和研究之用。

品質保證

該測試已取得試題持有者和第三方的授權,我們深信IT業的專業人員和經理人有能力保證被授權産品的質量。

輕松通過

如果妳使用NewDumps題庫,您參加考試我們保證96%以上的通過率,壹次不過,退還購買費用!

Try Before Buy

NewDumps提供每種産品免費測試。在您決定購買之前,請試用DEMO,檢測可能存在的問題及試題質量和適用性。