先試後買

購買之前,你可以先嘗試下載一個試用版本。目前我們只提供PDF版本的試用DEMO,軟件版本只提供截圖。

  • 全天候客戶支持,安全的購物網站。
  • 一年免費更新,以符合真正的考試場景。
  • 支付成功以后,你能在網站上立即下載所購買的產品。
問題1
When you assign material components using the BOM transfer function, the system uses the Reference Point field in the BOM items and activities to establish a logical connection between which items?
There are 2 correct answers to this question.
Response:

正確答案: B,D
問題2
Which method of revenue planning allows you to follow the same procedure as in hierarchical cost planning or can be entered by revenue element?
Please choose the correct answer.
Response:

正確答案: A
問題3
Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships?
Please choose the correct answer.
Response:

正確答案: D
問題4
Consider a scenario where you have started by displaying the planned costs for the entire project and how these planned costs are distributed among the various value categories for
WBS element WBS 2.
You then want to analyze the planned costs of WBS element WBS 2 for value category 620 according to cost distribution to the various periods.
Which type of reporting allows you to achieve this?
Please choose the correct answer.
Response:

正確答案: C
問題5
Which of the following type determines which type of orders a system can create during assembly processing?
Please choose the correct answer.
Response:

正確答案: A
問題6
Most of the reports in the SAP Project System can be refreshed without exiting or closing the report. Which report must be restarted to update the displayed data?
Please choose the correct the answer.
Response:

正確答案: B
問題7
A customer wants to maintain basic data and dates of a WBS element on the same tab.
Also, basic start and basic finish should be mandatory fields. What do you recommend?
There are 2 correct answers to this question.
Response:

正確答案: A,D
問題8
Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the execution phase you have an option to set the actual dates in the sameway in the project planning board.
What is the status that must be set before you can enter actual start and actual end dates?
There are 2 correct answers to this question.
Response:

正確答案: A,B
問題9
In requirements grouping which indicator must be set for WBS elements that determines whether the requirements may be grouped into one WBS element and how?
Please choose the correct answer.
Response:

正確答案: A
問題10
Which version serves as a proof of the project status in the past and also serves as a comparison with the operative project?
Please choose the correct answer.
Response:

正確答案: D
問題11
Which item category do you choose if you do not want to include the components in inventory management but want to use them immediately in the network?
Please choose the correct answer.
Response:

正確答案: A
問題12
Project System has its own Organizational structure, which can be a matrix structure.
Please choose the correct answer.
Response:

正確答案: A
問題13
In which type of settlement the costs of all the periods up to the one you specify in settlement are settled?
Please choose the correct answer.
Response:

正確答案: B
問題14
Workforce Planning in Project Systems, allows you to assign certain HR resources to activities of a project. Which of the following can be assigned?
There are 3 correct answers to this question.
Response:

正確答案: A,B,D

專業認證

NewDumps模擬測試題具有最高的專業技術含量,只供具有相關專業知識的專家和學者學習和研究之用。

品質保證

該測試已取得試題持有者和第三方的授權,我們深信IT業的專業人員和經理人有能力保證被授權産品的質量。

輕松通過

如果妳使用NewDumps題庫,您參加考試我們保證96%以上的通過率,壹次不過,退還購買費用!

Try Before Buy

NewDumps提供每種産品免費測試。在您決定購買之前,請試用DEMO,檢測可能存在的問題及試題質量和適用性。