問題1
Which of the following FIDIC contract forms require certification in the payment process? (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
Which of the following FIDIC contract forms require certification in the payment process? (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
正確答案: A,B
說明:(僅 NewDumps 成員可見)
問題2
(In FIDIC contracts, a number of time limits are included for the Parties and the Engineer to perform various obligations. How are failures to comply with these time limits most typically being dealt with in these forms of contracts? [2017 Edition] (1 correct answer))
(In FIDIC contracts, a number of time limits are included for the Parties and the Engineer to perform various obligations. How are failures to comply with these time limits most typically being dealt with in these forms of contracts? [2017 Edition] (1 correct answer))
正確答案: C
說明:(僅 NewDumps 成員可見)
問題3
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?
正確答案: A
說明:(僅 NewDumps 成員可見)
問題4
(For specific probable future events or circumstances which may adversely affect the Works, FIDIC Red and Yellow Books (edition 1999) provide a duty to notify specific parties. Which two statements are correct?
Choose all of the correct answers (multiple possibilities).)
(For specific probable future events or circumstances which may adversely affect the Works, FIDIC Red and Yellow Books (edition 1999) provide a duty to notify specific parties. Which two statements are correct?
Choose all of the correct answers (multiple possibilities).)
正確答案: C,D
說明:(僅 NewDumps 成員可見)
問題5
(Which two statements are correct for the FIDIC Red Book (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
(Which two statements are correct for the FIDIC Red Book (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
正確答案: A,D
說明:(僅 NewDumps 成員可見)
問題6
If defects are identified during the Tests on Completion, which one of the following options is not available to the Parties under the Contract?
If defects are identified during the Tests on Completion, which one of the following options is not available to the Parties under the Contract?
正確答案: A
說明:(僅 NewDumps 成員可見)
問題7
In case a Variation is initiated by the Engineer for prompt implementation ...... [FIDIC Red, and Yellow Books, 2017 Editions] Choose all of the correct answers (multiple possibilities).
In case a Variation is initiated by the Engineer for prompt implementation ...... [FIDIC Red, and Yellow Books, 2017 Editions] Choose all of the correct answers (multiple possibilities).
正確答案: C,D
說明:(僅 NewDumps 成員可見)
問題8
What does discharge confirm under the FIDIC Red Book (edition 1999)?
What does discharge confirm under the FIDIC Red Book (edition 1999)?
正確答案: A
說明:(僅 NewDumps 成員可見)
問題9
(Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to give notice to the Employer if it discovers errors or defects of a technical nature. Is this statement true or false?)
(Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to give notice to the Employer if it discovers errors or defects of a technical nature. Is this statement true or false?)
正確答案: B
說明:(僅 NewDumps 成員可見)