問題1
You are performing an SAP S/4HANA conversion. You are in the BIND PATCH phase of the Configuration roadmap step. For some software components, you find entries in the Calculated level column.
What does the Calculated level indicate for those software components?
You are performing an SAP S/4HANA conversion. You are in the BIND PATCH phase of the Configuration roadmap step. For some software components, you find entries in the Calculated level column.
What does the Calculated level indicate for those software components?
正確答案: B
問題2
What are the benefits of using the benchmarking option of the DMO for SUM? Note: There are 2 correct answers to this question.
What are the benefits of using the benchmarking option of the DMO for SUM? Note: There are 2 correct answers to this question.
正確答案: A,D
問題3
You are running an SAP ECC system with SAP BASIS 740, non-Unicode on SAP MaxDB. Which of the following are possible paths to perform an SAP S/4HANA conversion? Note: There are 3 correct answers to this question.
You are running an SAP ECC system with SAP BASIS 740, non-Unicode on SAP MaxDB. Which of the following are possible paths to perform an SAP S/4HANA conversion? Note: There are 3 correct answers to this question.
正確答案: B,C,D
問題4
Which of the following scenarios does Software Update Manager cover? Note: There are 2 correct answers to this question
Which of the following scenarios does Software Update Manager cover? Note: There are 2 correct answers to this question
正確答案: A
問題5
What SAP systems can you use for the ABAP Test Cockpit (ATC) to perform the custom code analysis for an SAP S/4HANA conversion? Note: There are 2 correct answers to this question.
What SAP systems can you use for the ABAP Test Cockpit (ATC) to perform the custom code analysis for an SAP S/4HANA conversion? Note: There are 2 correct answers to this question.
正確答案: C,D