問題1
Which of the following is the MAIN difference between an open-ended and a close-ended problem statement?
Which of the following is the MAIN difference between an open-ended and a close-ended problem statement?
正確答案: B
問題2
Due to external market conditions, the Chief Executive Officer (CEO) has announced a company shift in strategic priorities. As such, more focus will be spent on tuning current operational capabilities. Which of the following is the MOST likely outcome of an existing project that is currently in an initiation phase and about to enter stage-gate review and now falls outside of the new strategic priorities?
Due to external market conditions, the Chief Executive Officer (CEO) has announced a company shift in strategic priorities. As such, more focus will be spent on tuning current operational capabilities. Which of the following is the MOST likely outcome of an existing project that is currently in an initiation phase and about to enter stage-gate review and now falls outside of the new strategic priorities?
正確答案: B
問題3
A project manager has calculated their project to have a SV of -$5,000. Which of the following conclusions is correct?
A project manager has calculated their project to have a SV of -$5,000. Which of the following conclusions is correct?
正確答案: C
問題4
Within a corporation, project managers are assigned people based on defined roles and responsibilities. Project resources are temporarily provided to the project but still report the functional managers as well as the project manager. Which of the following styles of management is this also known as?
Within a corporation, project managers are assigned people based on defined roles and responsibilities. Project resources are temporarily provided to the project but still report the functional managers as well as the project manager. Which of the following styles of management is this also known as?
正確答案: C
問題5
A project manager is completing a project schedule network diagram using boxes to represent the project activities that are connected by lines to show their dependencies. Which of the following tools is the project manager using?
A project manager is completing a project schedule network diagram using boxes to represent the project activities that are connected by lines to show their dependencies. Which of the following tools is the project manager using?
正確答案: D
問題6
While working on a project, an unforeseen event arises that impacts a project objective. Which of the following should be updated as a result?
While working on a project, an unforeseen event arises that impacts a project objective. Which of the following should be updated as a result?
正確答案: A
問題7
During which of the following process groups is the project charter developed?
During which of the following process groups is the project charter developed?
正確答案: C
問題8
-- Exhibit - -- Exhibit -

Click on the Exhibit button. Which of the following is the float of the path: start-A-D-end?
-- Exhibit - -- Exhibit -

Click on the Exhibit button. Which of the following is the float of the path: start-A-D-end?
正確答案: D
問題9
In a functional structured organization, which of the following is a common cause of conflict with project team members?
In a functional structured organization, which of the following is a common cause of conflict with project team members?
正確答案: C
問題10
An unexpected risk has been identified in a project. Which of the following actions should the project manager perform FIRST?
An unexpected risk has been identified in a project. Which of the following actions should the project manager perform FIRST?
正確答案: D
問題11
Which of the following project documents lists risks and describes the strategy to deal with a risk?
Which of the following project documents lists risks and describes the strategy to deal with a risk?
正確答案: C
問題12
Which of the following is a document used iteratively during a project to capture strengths and weaknesses?
Which of the following is a document used iteratively during a project to capture strengths and weaknesses?
正確答案: B
問題13
Which of the following describes a critical path?
Which of the following describes a critical path?
正確答案: B
問題14
A project is nearing completion. Which of the following tasks is required to ensure continuity after the project closes?
A project is nearing completion. Which of the following tasks is required to ensure continuity after the project closes?
正確答案: A